|
Member
Login
|
|
|
|
"United We Stand"
|
|
Asian American Business Roundtable (AABR)
Rawlein G. Soberano. Ph.D., President
20224 Thunderhead Way Suite B
Germantown, MD 20874
Phone: (301) 601-9038
Toll Free: 1-866-215-4365 (PIN# 4766)
Fax: (301) 601-9430
Email: aabr89@aol.com
|
| |
|
WOODROW
WILSON BRIDGE PROJECT
Project
Overview
CONSTRUCTION
PROGRESS
(All
future construction dates subject to change)
|
BRIDGE
REPLACEMENT
 |
Dredge
Contract
completed February 2001 ($15 million)
|
 |
Bridge
Foundations Contract to Support the New Bridge’s 17 Pier - started
May 2001/completed July 2003 ($125 million)
|
 |
Bridge
Draw Span Contract started
in February 2003/scheduled completion in mid 2008 ($186
million)
x
Involves construction of the draw spans and two arches for
the new twin bridges (Inner & Outer Loops).
x
Formwork for Outer Loop span is currently underway and
progressing from south to north.
x
Majority of construction will occur on the Potomac River. |
 |
Virginia
Approach Contract started
in April 2003/ scheduled completion in mid 2008 ($115 million)
x Involves construction of the new twin bridges over
land.
x Ten
new foundations will be built at five pier locations to
support six new bridge arches. |
 |
Maryland
Approach Conract started
in June 2003/scheduled completion in mid 2008 ($191 million)
x
Involves consruction of the new twin bridges over water.
x
One new foundation will be built; nine new bridge arches
will be completed.
|
INTERSTATE
295 INTERCHANGE
 |
Ground
Improvement at Maryland Shoreline Contract started
August 2001/scheduled completion in late 2004
|
x
Involves strengthening soil on south side of I-95
North/Beltway between Rosalie Island near the Maryland shore
x
Temporarily adding levels of new soil to compress the existing
ground.
x
Finished ground will be elevated approximately 30-feet higher than
the Capital Beltway.
x
Work is more than 89 percent complete.
 |
I-295
Overpass Ramps to and from Maryland 210 (immediately east of
the bridge) Contract started December 2001/scheduled
completion in early 2004 ($42 million)
x
Involves replacing existing “s-curve” ramps with longer
overpasses to accommodate the wider future Beltway.
Work
includes building six new bridges and four retaining walls.
x
Completed the new construction of a new MD 210 to I-295
northbound overpass; currently building a new MD
RT-210
to I-295 southbound overpass. Both new overpass ramps to
open in late 2003.
x
Work is more than 68 percent complete. |
 |
Widening
of I-95N/Capital Beltway (Outer Loop) and Southern Access
Ramps Contract started
in December 2002/scheduled completion in mid 206
($45 million)
x
Involves building access ramps to and from the National Harbor
development, as well as widening I-95N/Capital
Beltway
(Outer Loop) to match new bridge and allow for interim
shifting of existing Beltway traffic to new six-
lane
southern bridge (Outer Loop), while new six-lane northern
bridge (Inner Loop) is being constructed.
x
Work includes building 11 new bridges and six retaining walls.
|
U.S.
ROUTE 1 INTERCHANGE
 |
Ground
Improvement Contract between Telegraph Road and U.S. Route 1 started
December 2001/scheduled completion in mid 2004 ($34.5
million)
x
Involves strengthening soil adjacent to the existing Capital
Beltway where the wider Beltway will be built.
x
Two soil stabilization methods being used: 1) Temporarily
adding levels of new soil to compress the existing
Ground; 2) Injecting cement and mixing it with existing
ground.
x
Work is more than 80 percent complete. |
 |
Demolition
of Hunting Tower Building Contract
started July 2003/completed April 2003 ($988,000)
|
 |
First
Phase of U.S. Route 1 Interchange “Tie-in” Contract started
in February 2003/scheduled completion in late 2007 ($55
million)
x
Involves replacing the existing Washington Street overpass
with a longer overpass to span the wider Beltway.
The
new overpass will feature four lanes bordered by wide
sidewalks, a bike/pedestrian path and extensive
landscaping.
x
In early August 2003, Washington Street will be reduced
temporarily from four lanes to three lanes from
Hunting
Creek to across the overpass. A reversible lane will provide
two lanes to accommodate the morning and
evening rush hours, as is currently available.
x
Also involves widening I-95N/Capital Beltway (Outer Loop) to
match new bridge and allow for interim shifting of existing
Beltway traffic to new six-lane southern bridge (Outer Loop),
while new six-lane northern bridge (Inner Loop) is being
constructed.
x
Currently removing two office buildings and three low-rise
Hunting Terrace Apartment Buildings, constructing
replacement parking and relocating temporarily a bike trail. |
 |
Southern
Ramp Bridges of U.S. Route 1 Interchange Contract started
in June 2003/scheduled completion in mid 2005 ($38 million)
x
Involves building bridges over Cameron Run and Hunting Creek
to align with the widened I-95N/Capital Beltway (Outer
Loop).
x
Also will build ramps connecting U.S. Route 1 and I-95/Capital
Beltway.
|
ADVANCED
INTELLIGENT TRANSPORTATION SYSTEMS (ITS)
 |
ITS
Contract started
in November 2002/scheduled completion in late 2003 ($1.5
million)
x
Involves building and installing overhead message signs on the
I-95/Capital Beltway within the Project area.
|
CONSTRUCTION
& PRINCE GEORGE’S COUNTY
 |
All
major construction projects have unavoidable impacts on local
communities, and the Wilson Bridge Project is no exception. By
working closely with Prince George’s Count officials and
other interested residents, our goal is to address and manage
those impacts, thereby minimizing adverse effects on the
county’s quality of life.
|
Construction
Affecting Prince George’s County
 |
Reconstruction
of overpass ramps that connect I-295 and MD 210 requires
occasional lane, shoulder and ramp closures during non-peak
travel times. Pile driving is required to build foundations
for these overpass ramps. Other activities include transport
of large equipment, hauling/placing of construction material.
|
 |
Construction
of new I-295 South ramps to the future National Harbor
development begins in Spring 2003. Road construction will be
evident to neighboring residents, including movement of heavy
equipment, materials and truck deliveries.
|
 |
Building
the new bridge requires construction activities on the
Maryland shore and Smoot Cove.
|
 |
Prince
George’s-Sensitive Construction
|
 |
In
close consultation with Prince George’s County elected
officials and staff, the Project has developed several
initiatives to ease construction impacts, including:
|
 |
Confinement
of Construction Activities – Many
activities that support construction are confined to fenced-in
staging areas located near the Maryland shoreline, immediately
south of the existing bridge and along I-295 Interchange and
on both sides of the Capital Beltway.
|
 |
Designated
Haul Rates – Workers and trucks must use Oxon Hill
Road, MD 210 and the Capital Beltway. Residential roads are
off-limits for parking of construction trucks and field
personnel.
|
 |
Hours
of Operation – The majority of construction will
occur during daylight hours (sunrise to sunset) Monday through
Friday, though some weekend and overnight construction will be
required. Contractors have been advised to make practical
efforts to confine noise-generating activities to daylight
hours. Sunday work will be permitted only if essential to
maintain the schedule.
|
 |
Noise
Restriction in Sensitive Areas – In construction
areas near residential neighborhoods, several noise
restrictions apply. South of the Beltway and I-295, pile
driving will only be permitted between 8:00am and 6:00pm,
Monday through Friday, from 9:00am to 6:00pm on Saturdays, and
no pile driving is permitted on Sundays.
|
 |
To
reduce the noise generated by safety back-up alarms on
construction vehicles, contractors are advised to minimize the
need for vehicles to back-up by attempting to circulate within
construction limits.
|
 |
Reducing
Vibration Effects – To protect nearby residents,
efforts are made to minimize vibration effects from
construction activities. Construction techniques that create
major vibration are prohibited close to residential
neighborhoods, and sensitive areas will be monitored wit
seismographs during critical operations.
|
 |
Early
Construction of Sound Wall – When construction
activities in the MD 210 Interchange area begin, an early
action item will be construction of sound walls.
|
 |
Privacy
Fence – An ornamental privacy fence will be erected
to buffer residences from construction of ramps and the
National Harbor development.
|
 |
Controlling
Dust in Neighborhoods – Dust is controlled b active
use of water trucks and hoses on haul roads and within work
sites.
|
 |
Commitment
to the Environment – Full-time, on-site construction
inspectors evaluate protection of the natural environment
through ongoing monitoring of contractors’ compliance with
federal, state and local guidelines and permits.
|
 |
Communication
with Directly Affected Communities – Targeted
outreach efforts, including personal phone calls and
locally-distributed flyers, facilitate information sharing
with communities that neighbor Project construction areas. On
an ongoing basis since 1998, we have met with a core of
citizen stakeholders to discuss a variety of timely issue. The
meetings are open to all interested citizens, with meeting
times and locations posted at www.wilsonbridge.com.
|
COMMUTER
OPTIONS
 |
With
several years of heavy construction ahead, County residents
are urged to consider alternative commuting options. For
comprehensive information on alternatives, click on www.wilsonbridge.com.
For Prince George’s transit routes and schedules, please
contact: METRO, (202) 637-7000, TTY (202) 638-3780; www.metroopendoors.com.
|
 |
CONTACTS:
Woodrow Wilson Bridge Project, Norine
Walker, 2901 Eisenhower Avenue, Unit C, Alexandria, VA 22314;
(301) 686-0000 / (703) 329-0300.
|
 |
Prince
George’s County, Erv
Beckert, Department of Public Works & Transportation, 9400
Peppercorn Place, Suite 420, Largo, MD 20774; (301) 883-5710.
|
 |
Stay
informed of Project developments, construction hours,
schedules and major activities by: Clicking www.wilsonbridge.com,
calling (301) 686-0000 or (703) 329-0300.
|
(As
of July 2003)
DOT's
Mid-Atlantic TEAM Website |
|